Water Engineering (Beijing) Co.,Ltd. has won the bidding of Inner Mongolia
Bayan Nur No.2 WWTP and water reuse project in October 2012. It’s a KFW
bank-loan project and the contents of the project include the construction of a
new wastewater treatment and water reuse plant. The capacity of the WWTP is
100,000 m3/d, and the effluent standard is Class IB of “Discharge Standard of
Pollutants for Municipal Wastewater Treatment Plant”. 60,000 m3/d of the
effluent is tertiary-treated for reuse. GreenTech is in charge of the
procurement, supply, installation, commissioning and relevant services of all
equipment for wastewater treatment, water reuse and sludge disposal.