Welcome GREENTECH!
2013-07-11
GreenTech Passed the 72h Performance Test of Beijing Qinghe Water Reuse Plant-Phase II Water Reuse Project
GreenTech Water Engineering (Beijing) Co., Ltd. successfully passed the 72 hour performance test for Phase II Water Reuse Project of Beijing Qinghe Water Reuse Plant in June, 2013. The total design capacity of this project is 320,000m3/d . Among that, 180,000m3/d of membrane treatment system is undertaken by GreenTech. The operation of the Water Reuse Plant is stable and each parameter meets the design requirements. Permeability is 400-800L/.hr.bar,and the stable TMP is 0.05-0.1bar. The successful performance test indicates professional system design, accurate installation and quality commissioning.